Here is an Alex update for you and all the others that are waiting so
patiently.
The toroid manufacturing is scheduled to complete and ship to TAPR on
April 26th.
The potential long lead time items (ICs) are in the process of being ordered.
The PCBs are awaiting one final test round before they will be ordered.
The procedure is as follows (this is a very simplified list):
1. Receive and inspect the toroids
2. Install one set on existing PCBs
3. Re-test to make sure we have everything right
4. Order the rest of the parts and the PCBs
5. Open the order page
6. Manufacture and test
7. Ship them out!
I would really like to have the order page up by Dayton (May 14), but
a lot has to happen in the next four weeks. The lead in to Dayton is
always very busy, so I am going to guess that the order page will be
up just after Dayton, i.e., in the last 2 weeks of May.
Hope this helps, and thanks to everyone for being patient.
If you make it to Dayton, please stop by the TAPR booth, TAPR forum
and/or SDR forum and say hello.
73,
Scotty WA2DFI
At 10:23 2010-04-13 +0200, Isaac Weksler wrote:
>***** High Performance Software Defined Radio Discussion List *****
>
>
>I am in the process of ordering a complete HPSDR set. At the moment
>the Alex board is the only one that seems no to be available. Any
>news about its availability? At TAPR or otherwise?
>
>73. Isaac 4Z1AO
1271180015.0
More information about the Hpsdr
mailing list